The 941 m long viaduct, which consists of two parallel bridges, crosses the Becva River, the Olomouc – Přerov railway line, the chemical plants and the green vitriol dump. The 21‑span bridges are formed by pairs of steel girders and a reinforced concrete slab. In view of the corrosive effects of green vitriol, in the central part of viaduct the I girders transfer into narrow box girders and the piers were cast into UHPC precast shells. The beams were assembled on erection towers, then the bridge slab was incrementally concreted.
Structure length
941.00 mLocation
Motorway D1 near a city of PrerovSpan length
30.00 – 69.00 mStructure type
Continuous composite structures.Width of the superstructure
2 x 14.95 mScope of work
Detailed design.
MAP
GPS:
49.4511776N, 17.4183034E