The bridge, which crosses a local creek, a rural road and a bio‑corridor is situated in the area with a very poor geotechnical condition and in the place where the motorway’s fill has a depth of 14 m. Therefore, the bridge is formed by a statically determined structure assembled of simple precast beams and a composite slab, and the fill is from polystyrene. Due to the heavy load the girders and slab are from a high‑strength concrete.

Structure length

36.5 m

Location

Motorway D1 near a village of Brnenske Ivanovice

Span length

34.8 m

Structure type

Composite precast structure.

Width of the superstructure

47.5 m

Scope of work

Design for construction permission, Tender design, Detailed design.

MAP

GPS: 49.2989259N, 17.1104536E