Bridge across the Bohumin streamlet and railway track

Completed in 2011

The bridge of three spans is suspended on two pylons. The deck is formed by two edge girders mutually connected by floor beams and a composite deck slab.

Structure length

140.3 m

Location

Bohumin, Roadway I/67, Czech Republic

Span length

30.0 + 70.0 + 30.0 m

Structure type

Cable-stayed bridge.

Width of the superstructure

15.90 m

Scope of work

Design for zoning approval, design for construction permission, bid design.

MAP

GPS: 49.9050126N, 18.3674964E
zobrazit na mapy.cz

AWARDS

Bridge of the year 2011. Ministry of Transport 2013.